CAT III AGL Landing System

Department

Aviation

Client

Perth Airport Pty Ltd

Time

Jan 2016 to June 2017

Value

Approx $30m

Team

WCC

  • Daniel Laudehr
  • James Webb
  • Kevin McSweeney
  • Ryan Oliver

Safegate

  • Damian Browne
  • Jerry O'Sullivan
  • Josh Hay
  • Anthony Collins

Scope of Works

  • 1,200No. SIT and Structural Pits
  • 90KM of Primary and Secondary Trenching
  • 3No. New ALER Rooms
  • 3,800No. Inset Lights
  • 700KM of Primary & Secondary Cable
  • RWY 21 ALS Design & Construct
  • RWY 0321 Central 16m Overlay and Grooving
  • 3No. ALER Buildings

Project Features

What is CAT III?

A category of a Precision Approach Landing System that allows a Decision Height for approach to be made at 125m

Current YPPH Operations are an Instrument Precision Approach CAT I which requires a Decision Height at 550m

This in am Infrastructure sense means:

  • Approach Lighting System with a 300m cross bar and centre line barrettes
  • REL at 60m spacing's Inc. MIRL and HIRL Options
  • Taxiway centre line lights at 60m on straights and 15m curves

6,500 Services potholed and No Service Strikes

80,000 Man Hours No LTI's

Further Information

Read about the project on the ADB Safegate blog.

Watch a 2 minute video describing the CAT-III upgrade project.

CONTACT DETAILS

WEST COAST CIVIL

25 Ross Drive,
Perth Airport 6105

office@westcoastcivil.com.au


Copyright © 2025

 

 

 

NETWORKING

LinkedIn LinkedIn


wcc-logo-001.svg