KBJ to Puma - White Oil Line

Department

Civil

Client

Taylors Engineering

Time

September 2021 to June 2022

Value

Approx $4.5m

Team

Ken O'Connor, Liz Gomez, Brendon Kerr

Scope of Works

Stage 1:

  • 1,113m Open Trenching
  • 100m of Mircotunnelling

Stage 2:

  • 60m Open Trench
  • 160m Mircotunnelling

Project Features

  • Long Term Dewatering to Support Microtunnelling Operations
  • Mircotunnelling under Rail Corridor and Operationally Important Road Reserve
  • Stakeholder Interaction through Pipeline Easement