PP2 Bag Storage Expansion Works

Department

Civil

Client

CSBP

Time

October 2025 to December 2025

Value

Approx $1m - $2m

Team

Ken O'Connor, David Romaine, Brendon Kerr, Emilija Jasevskaja

Scope of Works

  • Earthworks: Completed bulk cut-to-fill operations to achieve the required civil design levels, including preparation of the subgrade for subsequent construction activities
  • Pavement Construction: Constructed a new pavement to expand the ammonium nitrate storage area. Works included placement of recycled road base (sub-base), MRWA base course, chip seal, and asphalt in accordance to design requirements
  • Fire Main Installation: Installed and commissioned a new HDPE fire-water piping system and fire hydrants, including connection into the existing active water system
  • Drainage: Constructed a swale drain lined with BGM liner and extended existing sump to tie into existing drainage system.
  • Site Infrastructure: Installed new security fencing and gate, apron lighting, and completed line-marking to the newly constructed pad

Project Features

  • Achieved a cut-to-fill balance using on-site materials, removing the requirement for imported fill and optimising site resources.
  • Implemented recycled materials for the sub-base layer, reducing environmental impact while delivering measurable cost savings for the client.
  • Successfully delivered works within a live, operational major hazard facility storing ammonium nitrate, maintaining safety and uninterrupted operations.
  • Completed all works to specification and achieved all milestones within a tight construction timeframe.
  • Successfully connected and integrated all required services, including fire water and lighting into the existing network to support the expanded storage pad.