NAAN2 Tertiary Abatement Works 

Department

Civil

Client

CSBP

Time

October 2025 to December 2025

Value

Approx $650k

Team

Ken O'Connor, David Romaine, Joe Power, Ryan Ward

Scope of Works

  • Foundations: Completed excavation, compaction, and backfilling works to prepare for new structural foundations.
  • Service Management: Exposed and provided temporary support for existing communications services during construction operations.
  • Structural Works: Constructed new footings and support pedestals in accordance with design specifications.
  • Reactor Foundation: Delivered the new reactor foundation, including installation and alignment of the anchor bolt template.
  • Pavement Works: Constructed new reinforced concrete and asphalt pavements to suit final site requirements.

Project Features

  • Risk-Managed Construction: Delivered new foundations adjacent to critical communications and high-voltage cables without causing any service disruptions.
  • Program Performance: Achieved project completion three weeks ahead of the scheduled delivery date.