Sodium Cyanide Expansion

Department

Civil

Client

CSBP

Time

April 2025 to January 2026

Value

Approx $6m - $7m

Team

Ken O'Connor, Joe Power, David Romaine, Ryan Ward

Scope of Works

  • Bulk earthworks to prepare the site for civil and structural works.
  • Construction of temporary and permanent roadworks to support site access and final design requirements.
  • Demolition and reinstatement of existing concrete and asphalt pavements as required.
  • Fabrication and installation of underground carbon steel piping for the cooling water system.
  • Installation of underground HDPE piping for the fire water system.
  • Installation of a new earthing grid system for electrical grounding compliance.
  • Construction of new reinforced concrete support foundations for equipment and infrastructure.
  • Construction of a raft slab foundation for the new reverse osmosis system.
  • Installation of a new structural steel frame for the cooling tower.

Project Features

  • Achievement of key critical shutdown milestones in accordance with project programme requirements.
  • Completion of construction works in proximity to live services without disruption to ongoing plant operations.
  • Incorporation of recycled crushed concrete as imported fill material to support sustainable construction practices and cost efficiencies.
  • Installation of cooling water piping adjacent to existing high-voltage infrastructure utilising a controlled dual-crane lifting methodology.
  • Placement of 400m³ of concrete in a single continuous pour using a multi-pump arrangement to maintain pour continuity and quality control.