Air BP Fuel Lowering
Department
Aviation
Client
BP Australia Pty Ltd
Time
January 2024 to 31 December 2024
Value
Approx $2m
Team
Ken O'Connor, Brendon Kerr, Wilmar Aza
Scope of Works
- Obtain all required work permits from PAPL and BP, including airside access and safety inductions.
- Mobilise and establish the site, including installation of fencing, water-filled barriers, and site offices.
- Ensure site setup complies with airside restrictions and avoids aircraft jet blast zones.
- Implement dewatering and dust suppression systems as required.
- Carry out site survey using AHD (Australian Height Datum) and the Perth Coastal Grid.
- Install temporary utilities and manage controlled access crossings.
- Ensure no damage to existing pipelines, no safety or environmental incidents, and maintain uninterrupted supply of Jet A-1 fuel.
Project Features
- Excavate along the pipeline route (chainage 3500 to 3435) to expose the existing pipeline.
- Install culverts at Link 8 and Link 9 taxiways.
- Lower the pipeline in a controlled sequence to ensure clearance beneath new RCP drainage structures at locations P1, P2, P3, and P4.
- Cover the pipeline with clean fill material and install marker tape.
- Backfill over the pipeline in compacted layers to achieve the specified Proctor density.
- Conduct an as-built survey to confirm final pipeline depth.
- Replace all pipeline markers to reflect updated alignment and depth.