Asphalt Plant - Civil Works
Department
Civil
Client
Fulton Hogan Industries
Time
September 2021 to May 2022
Value
Approx $5m
Team
Michael Collins, Dave Dunne
Scope of Works
- Groundworks Inc Underground Services, Excavations and Formation Prep.
- Form and Pour 2,700m3 of Concrete
- Supply & Lay 350t of Steel
- Reinstatement of Pavements
- Facilitate Install and Commissioning of Plant
Project Features
- Consolidation of Foundation Design Post Ward
- First Installation of this sort of Processing Plant in Aus
- Cost Pressures on Rising Steel Prices and Budget Management with Client
- Operational Facility Adjacent